What you do not know without investigations
Before the investigations, the cost of the foundations is an assumption. Nobody knows the bearing capacity of the ground, its deformability, the groundwater level, the presence of made ground or compressible layers, or even the subsoil category that enters the seismic calculation. Each of these unknowns can shift the solution from a shallow raft to deep foundations, and the cost along with it.
On the apartment building (palazzina) of the guide to reducing construction costs, the foundations are those of the reference basement, 408 m² at a depth of about 3.5 m. The blog gives no per-m² value for the raft foundation (platea) of an apartment building with a basement: the only figure it publishes concerns the raft of a prefabricated house, a different element in thickness and loads. Over the 408 m² of the example the raft is estimated from the quantities of a preliminary sizing and the prices of the regional price list, and even then it remains the favourable assumption, the one without piles and without groundwater.
What the standards require
The Technical Standards for Construction (D.M. 17 January 2018) devote chapter 6 to geotechnical design. Design choices must take account of the characteristics of the subsoil and of the context, and the design is based on the geological modelling of the site and on geotechnical investigations proportionate to the works (§ 6.2.1 and § 6.2.2). The investigations are therefore not an option for containing risk: they are a prerequisite of the structural design.
Two distinct documents follow from this, with different authors and contents: the geological report (relazione geologica), which describes the site, and the geotechnical report, which sizes the foundations on the basis of the investigations. Confusing them often leads to commissioning the first in the belief that the second is included, and to discovering late that tests or boreholes needed for the sizing are missing.
When to commission them
Investigations are worth most before the decisions are fixed. Commissioned after the purchase of the plot but before the architectural design, they make it possible to decide on the basement, its depth and the foundation solution with real data. Commissioned after the building permit, they confirm or contradict a design that can no longer be changed at no cost.
The rule the blog gives for the detached house applies all the more to an apartment building with a basement: geology before buying the plot is the cheapest insurance for the project, as the page on the cost of building a detached house points out. When the purchase cannot be made conditional on full investigations, a minimum campaign, with at least one borehole and a groundwater measurement, already removes the largest part of the uncertainty.
Three soils, three foundations
The table compares three ground assumptions on the same apartment building, with the same basement. The effect on cost is shown as a direction rather than an amount, because it depends on the investigations:
| Ground | Likely foundation | What is added | Effect on cost |
|---|---|---|---|
| A. Load-bearing ground, deep groundwater | Raft or inverted beams under the basement | Nothing in particular | Reference, to be estimated from the quantities of the raft |
| B. Load-bearing ground, groundwater above excavation level | Raft and watertight walls | Dewatering on site, watertight tank, possibly uplift measures | More expensive, especially for waterproofing and site works |
| C. Compressible layers below excavation level | Piles under a raft or pad foundations | Piles, test piles, special plant | Markedly more expensive, an item that can exceed the raft itself |
None of these assumptions is chosen at the desk. Case B often makes it worthwhile to reduce the depth or extent of the basement, the subject of the page on the cost of an underground garage. Case C shifts the focus to the loads: a lighter building or better distributed loads can reduce the number of piles, and the structural grid comes back into play.
The weight of the seismic zone
The subsoil category, derived from the investigations, enters into the definition of the design seismic action. An unfavourable subsoil category amplifies the action and weighs on the whole structure, not only on the foundations. It is another reason to have the investigations before preliminary sizing.
The allowance to hold before the geotechnical report
Until the investigations are available, the cost of the foundations should be written as a range and accompanied by a dedicated allowance, separate from general contingencies. In the example, the estimate concerns the raft under the 408 m² of the basement, and the allowance must cover at least the gap towards case B if the context suggests high groundwater. Case C cannot be covered by an allowance: if it is plausible, the investigations must be carried out before any other decision.
How to size the allowance by stage, and how to release it as the unknowns close, is covered on the page on how much to set aside for contingencies. A ground allowance that closes with the geotechnical report is one of the clearest cases of an allowance to be released stage by stage.
In summary
The cost of the foundations cannot be known without investigations, and the Technical Standards for Construction make them a prerequisite of the design. Commissioned before the architectural design, the investigations decide the basement, the foundation solution and part of the seismic action. Until then, the cost should be held as a range with a dedicated allowance.
Nature of the values quoted
Standards are quoted from their text. Areas and depths come from the example project, on fictitious assumptions, and the page gives no prices: it does not replace the geotechnical report or a priced bill of quantities (computo metrico estimativo).
Sources: Gazzetta Ufficiale, D.M. 17 January 2018, Technical Standards for Construction, chapter 6, § 6.2.1 and § 6.2.2.