Structure and building works: the item you do not negotiate
In residential construction, structure and building works account for between 40 and 45 per cent of the construction cost, according to the blog's construction cost breakdown. It is the largest item and the least negotiable: the structure is sized under the Technical Standards for Construction (Norme tecniche per le costruzioni, D.M. 17 January 2018), with the seismic actions of the site, and the margin for negotiating prices is thin. The real margin lies in the quantities, that is, in the decisions the designer makes before the calculation.
On the apartment building of the guide to reducing construction costs, the structure includes the foundations, the basement retaining walls, columns and shear walls, five floor decks (the ground-floor slab over the basement, three intermediate floors and the roof), the stair core and the lift shaft. The stair core with the lift, which the blog estimates at between 60,000 and 120,000 euros as a lump sum (a corpo) in apartment buildings, is also the rigid core that takes the horizontal actions: its position matters as much as its size.
The garage grid against the flat grid
The typical conflict in an apartment building with a basement is between two logics. Below, the lock-up garages (box) call for a regular spacing of about 2.5 m per space, clear bays in front of the doors and an aisle without columns. Above, the flats call for walls where kitchens, bathrooms and bedrooms need them, not where the garages need them.
| Decision | What it entails | Effect on cost |
|---|---|---|
| Columns aligned with both logics | Grid studied jointly by architect and structural engineer, for example a 5.0 m spacing (two garages) | Loads taken straight down to the foundations, no transfer |
| Flat columns placed freely, picked up at ground floor | Transfer beams in the ground-floor slab | Deep beams, more steel, more formwork, greater basement height |
| Garages without intermediate columns | Spans of 7-8 m in the ground-floor slab | Thicker or prestressed slab, more concrete |
Transfer beams are paid for three times: for their quantity of concrete and steel, for the height they take from the basement or the excavation, and for the complexity of the pour. Aligning the grids at feasibility stage costs nothing; achieving the same result after the architectural design costs a revision of the floor plans.
Slab spans
On a building 12.5 m deep, two bays of 6.25 m or three bays of about 4.2 m give slabs of different thickness and reinforcement. Longer spans free up the floor plans and reduce the number of columns, but call for thicker and heavier slabs, which in turn load columns and foundations. The choice is made by comparing the quantities of the two layouts on a typical floor, not on the average cost of the structure.
Cantilevers
Cantilevered balconies and loggias are both a structural issue and an envelope issue. A deep cantilever calls for heavier reinforcement, thermal breaks at the junction with the slab and careful waterproofing. Balconies carried on light brackets or loggias set within the volume change the problem; each solution has effects on the facade, covered on the page on the cost of the facade.
Shear walls, frame and seismic design
In Italy the structure is designed for the seismic action of the site, and the regularity of the building counts in the calculation. The NTC 2018 distinguish between buildings that are regular and irregular in plan and in elevation (§ 7.2.1), and an irregular building generally calls for more onerous checks and sizing. Compact plans, rigid cores in a central or symmetrical position and floors stacked without setbacks are shape decisions that also help the structure.
| Layout | Where it works | Point to watch |
|---|---|---|
| Beam and column frame | Plans that change from floor to floor | Downstand beams in the rooms, joints to be detailed carefully in seismic zones |
| Reinforced concrete shear walls | Repeated plans, walls between flats | High stiffness, less freedom for future alterations |
| Mixed, with a rigid stair core | Standard apartment buildings | Position of the core to be fixed early |
What to decide at feasibility stage
Four decisions are enough to avoid most structural extra costs: the grid shared by garages and flats, the position of the stair core, the depth of the cantilevers and regularity in elevation. They are architectural decisions more than calculation ones, and for that reason they must be taken with the structural engineer alongside the architect, not afterwards.
The rest follows. With the grid fixed, the structural engineer can provide at feasibility stage a preliminary sizing of slabs, columns and foundations, and therefore quantities of concrete, steel and formwork to be priced with the regional price list (prezzario). The relationship with the ground, which decides the type of foundation, is covered on the page on foundations and the geotechnical report.
In summary
The reinforced concrete structure, together with the building works, accounts for between 40 and 45 per cent of the cost of an apartment building, and there is little to negotiate. The margin lies in the grid: garages and flats aligned, no transfer beams, reasonable spans, measured cantilevers and a regular building. These are decisions to fix at feasibility stage, with the structural engineer.
Nature of the values quoted
Standards are quoted from their text. Dimensions and bays come from the example project, on fictitious assumptions, and the cost shares are those of the blog: they do not replace the structural calculation or a priced bill of quantities (computo metrico estimativo).
Sources: Prices given as examples, established in November 2026 from public references: cost shares and lump-sum items from the pages of this blog on the cost breakdown and on apartment buildings, 2026 · D.M. 17 January 2018, Technical Standards for Construction, § 7.2.1.