The example basement: 12 garages on 408 m²
The apartment building (palazzina) of the guide to reducing construction costs has 12 flats and a footprint of 24.0 m by 12.5 m. The reference assumption provides one garage per flat. Geometry decides straight away: a garage measures about 2.5 m by 5.0 m, a two-way manoeuvring aisle needs around 5 m, and two rows of garages either side of the aisle therefore take up about 15 m of net width, walls excluded.
Under a footprint 12.5 m deep there is room for a single row of garages along an aisle. Once the stair core with the lift, the fire lobby and a plant room are deducted, about seven garages remain over the 24 m of length. To get 12, the reference basement extends 4.5 m beyond the footprint under the courtyard and measures 24.0 m by 17.0 m, that is 408 m².
| Item | Reference basement |
|---|---|
| Dimensions | 24.0 × 17.0 m = 408 m² |
| Part under the building | 300 m² |
| Part under the courtyard | 108 m² |
| Garages | 12, in two rows of six |
| Excavation depth | about 3.5 m |
| Excavation volume | about 1,430 m³, without the battered slopes |
| Retaining walls | 82 m of perimeter, about 290 m² |
What a basement brings with it
The "per garage" price found in sales offers describes the product being sold, not what gets built. The table lists the works that the basement drags in, almost all of them absent from surface parking:
| Work | What makes it grow | In the example |
|---|---|---|
| Excavation and removal of spoil | Volume, type of soil, distance to the tip | About 1,430 m³ plus the slopes |
| Temporary support works | Buildings or roads close to the edge of the excavation | Battered slopes if space allows, otherwise a retaining wall of piles or sheet piles |
| Retaining walls and foundation | Earth pressure, presence of water | About 290 m² of wall, 408 m² of raft or foundations |
| Slab under the courtyard | Part outside the footprint | 108 m² of slab with waterproofing, drainage and soil |
| Waterproofing | Groundwater, seepage water | System to be chosen after the site investigations |
| Ramp | Level difference and gradient | About 3.5 m to climb, a ramp of some twenty metres |
| Fire prevention | Covered area of the car park | Above 300 m², a regulated activity |
Groundwater changes the order of magnitude of the basement more than any other item. If the investigations find it above the excavation level, dewatering is needed on site along with a permanent watertight tank, and the question moves from the parking page to the one on foundations and the geotechnical report.
The 300 m² threshold
Public and private car parks (autorimesse) with a total covered area above 300 m² are activities subject to fire prevention inspections (D.P.R. 151/2011, Annex I, activity 75). In the example, the 12-garage car park, once the stair core and plant room are deducted, is slightly above this threshold. Crossing it is not just paperwork: it entails a fire safety design, compartmentation, ventilation, escape routes and periodic inspections, that is, construction and running costs.
Reducing the basement so that the car park falls back below 300 m² therefore has a double effect. It reduces excavation, walls and the slab outside the footprint, and it takes the car park out of the regulated activities. This must be checked with the fire safety engineer, because the area to be counted depends on how cellars, plant rooms and the stair core are separated.
The grid imposed on the flats
The garages impose a grid of columns or walls at regular spacing, which has to be compatible with the walls of the flats above. When it is not, the loads are transferred by beams in the ground-floor slab. The subject is covered on the page on the structural grid and the cost of reinforced concrete.
Three ways of arranging the 12 parking spaces
The table compares three solutions on the same building. The solutions with surface spaces assume that the plot and the planning instrument (strumento urbanistico) allow it:
| Solution | Underground garages | Surface spaces | Basement | Effect on cost |
|---|---|---|---|---|
| A. Reference | 12 | 0 | 408 m², 108 m² outside the footprint | Reference |
| B. Basement within the footprint only | 7 | 5 | 300 m², no slab outside the footprint | Less excavation, fewer walls, no slab under the courtyard, car park below the threshold |
| C. No basement | 0 | 12 | none | No excavation, but about 300 m² of the plot taken up by parking spaces and aisles |
Solution B shows what the average cost of a garage hides. The seven garages under the building share with it the ground-floor slab, which is built anyway. The five garages under the courtyard carry on their own a waterproofed slab, an extra length of retaining wall and the fire safety threshold: their marginal cost is well above the average.
Solution C removes the basement but uses up the plot. Those square metres are lost to green space, to the permeable area required by the building regulations (regolamento edilizio) or to buildable floor area, and the choice is judged on the balance sheet of the development as well as on the cost of the works. On a narrow urban plot it often does not exist.
The rule on parking for new buildings
Planning law requires new buildings and their appurtenant areas to set aside parking space of not less than one square metre for every ten cubic metres of construction (Law no. 1150 of 17 August 1942, art. 41-sexies). In the example, 3,600 m³ above ground call for at least 360 m² of parking. Municipal and regional regulations may require more, for example one space per dwelling, and must be read before deciding on the basement.
The rule does not require the parking to be underground: it can also be on the surface within the appurtenant area. It is this freedom that opens up solutions B and C, when the plot allows it. The items specific to multi-family housing, including parking standards, are listed on the page on the cost of building an apartment building.
In summary
An underground garage costs for what it drags in: excavation, walls, waterproofing, ramp, fire prevention and structural grid. Under a 12.5 m footprint there is room for a single row of garages, and extra garages mean extending beyond the footprint, at the highest marginal cost of the basement. Before drawing it, it pays to read the parking rule for new buildings and the municipal regulations, and to check the 300 m² threshold.
Nature of the values quoted
Thresholds are quoted from their text. Dimensions, volumes and the number of garages come from the example project, calculated on fictitious assumptions: they do not replace the design of the car park or a priced bill of quantities (computo metrico estimativo).
Sources: Normattiva, Law no. 1150 of 17 August 1942, art. 41-sexies; D.P.R. 1 August 2011, no. 151, Annex I, activity 75.