Blog

The bill of quantities from a BIM model

📐 Focus5 min read

Extracting quantities from an information model rather than taking them off drawings looks like a solution to the measurement problem. In part it is, and it introduces a different problem: the geometry of the model and the measurement conventions of the prezzario do not coincide, and that gap has to be managed.

The regulatory context

The Italian public contracts code provides for the adoption of digital information management methods and tools for the design and delivery of projects above a given value threshold, with effect from 1 January 2025 for works exceeding one million euros. The detailed arrangements are set out in the dedicated annex.

To this is added the capitolato informativo, the employer's information requirements document, introduced into Annex I.7 by Legislative Decree 209 of 2024. It defines the general and specific information requirements needed for digital management of the project, and therefore establishes the level of detail and reliability at which quantities must be extractable from the model.

That second point is what directly concerns whoever prepares the bill. A model developed without explicit information requirements on quantities produces an extraction that is formally correct and unusable.

What the model returns and what it does not

Category Extractable from the model To be added manually
Structure Concrete volumes, reinforcement weights where modelled, formwork areas Complex formwork, staged pours, temporary works
Envelope and partitions Areas and volumes of the elements Treatment of surrounds, junctions, unmodelled elements
Finishes Areas by type Extras for work to small areas and at height
Services Network lengths, number of fittings and terminals Supports, penetrations, notional network allowances in outlet point bases
Excavation and earthworks Geometric volumes Actual versus theoretical section, operational widening
Site charges Nothing Scaffolding, protection, handling, safety charges

The last row matters most. A model describes the finished works, not the process delivering them, and items tied to the process remain entirely to be built. On a refurbishment project the share of the bill not derivable from the model can be substantial.

The critical point: matching objects to items

Extracting quantities is not the difficult step. The difficult step is matching the objects in the model to the items in the prezzario, and the reason is that the two systems classify reality differently.

The model groups by construction element. The prezzario groups by operation. A wall modelled as a single object corresponds to several prezzario items, from the masonry to plaster on two faces to decoration, and each of those items has its own measurement basis.

This is where the principal risk sits. The area the model returns is the geometric area of the element. The quantity the prezzario requires may be one measured on a different convention, with deductions for openings, dimensional thresholds and extras for working the surrounds. Applying the geometric figure without checking the basis produces a systematic divergence across the whole category.

Managing the gap

Three measures substantially reduce the risk. They concern modelling, coding and checking.

The first is defining the correspondence between objects and items before modelling rather than after. If the structure of the model is conceived for extraction, the correspondence becomes a stable table; if it is conceived only for representation, every extraction requires manual reconciliation.

The second is checking the prezzario measurement basis for the categories with the greatest incidence, and adjusting the extraction accordingly. The critical categories are always the same: plaster and finishes for deductions, excavation for the reference section, services for the choice between length and outlet point.

The third is recording the provenance of every quantity, distinguishing those extracted from those added manually. That is the information needed when the model is updated: the former regenerate, the latter have to be reviewed.

The link with the construction stage

Where digital information management tools are used, the works supervisor ensures the correlation between the accounting records and the information models produced or updated during construction. The correlation must be set up before work starts.

A demand for structural consistency follows that concerns whoever prepares the bill. If the accounts will correlate to the model, the structure of the items and their correspondence with the parts of the works must be settled once and settled stably, because every divergence between the structure of the bill and that of the accounts is paid for at every interim valuation.

Note: the legislative references in this page relate to Italy and are current as at the date of publication. Public procurement rules change frequently, and the version in force should be checked before any operational use.

Frequently asked questions

It is more traceable and quicker to update. It is reliable to the extent that the correspondence between objects and items has been checked and the prezzario measurement bases have been observed.

All those tied to the construction process rather than the finished works: temporary works, handling, protection and safety charges.

No, the rules referred to concern public contracts above the threshold. In private work adoption is a choice.

The computo metrico estimativo: from preparation to price books and specification